Legend
Northern lines (Continues to Airport Line)
4.5 km Albion (2)
Breakfast Creek
Ferny Grove line
2.7 km Bowen Hills (1)
Exhibition line
Exhibition station (1)
0.8 km Roma Street station (1)**
0.0 km George Street station (1)
0.0 km Woolloongabba station (1)
Continue to Park Road and City stations
5.9 km Dutton Park station (2)
Southern Lines (Continues on Gold Coast line)

The BaT (Bus and Train) project was a proposed north-south tunnel that would provide bus and rail modes of transportation together in an intuitive design by combining a new underground rail line and busway in a single, double-decked, 15m-wide tunnel beneath the Brisbane River and Brisbane central business district. The tunnel was to have three underground stations at Woolloongabba, George Street and Roma Street with Dutton Park upgraded.

The BaT project was planned to be a critical new link in South East Queensland’s public transport network by creating new major transport hubs across the city and inner city suburbs, and facilitating existing locations such as The Gabba, and the new Queen's Wharf development on George Street.[1]

Following a change in State Government, the project was cancelled in March 2015 and replaced by a new Cross River Rail proposal.

2013 plan

In November 2013, the Queensland Government announced a revised plan for the BaT (Bus and Train) project as an alternative to the previous Cross River Rail proposal. The revised plan involved a 14.8m external diameter (13.5m internal diameter) 5.4 kilometres (3.4 mi) tunnel to accommodate both a dual track rail line on the lower level and a two lane busway above. The cost was expected to be $5billion with construction proposed to start in 2015 and completion in 2021.[2][3] Citytrain patronage is quoted as having increased at an annual average of 3.4% between 2006–12, compared to an average annual population increase of 2.4% over the same period, confirming forecasts that the Merivale Bridge will reach capacity some time between 2016-2021.

The proposal commenced in the vicinity of Dutton Park station, with two new underground stations at Woolloongabba (adjacent to The Gabba) and George Street (in the CBD) adjacent to a proposed casino redevelopment site. The balance of the proposal involved the previously proposed underground station at Roma Street and the line connecting to the Exhibition line near Bowen Hills. The Underground stations were to also be busway stations. The southern end of the busway was proposed to connect directly to the existing Eastern Busway, with the northern end then proposed to connect to the Northern Busway via a bridge over the railway and adjacent Inner City Bypass motorway.

The stations were proposed to have 175 metre platforms to cater for future seven carriage trains, with the peak hour headway of 2.5 minutes between trains giving a notional capacity of 24 trains per hour in each direction. This was proposed to facilitate an increase in Gold Coast line services by 80% when it opened, and was also stated as catering for the 'Hillcrest (New Beaudesert) line by 2031'. That proposed line involves converting the existing standard gauge line from the Acacia Ridge freight terminal (just south of Salisbury station) to dual gauge. Hillcrest is a suburb west of Browns Plains and north of Greenbank. The standard gauge line passes west of Beaudesert on its way to the New South Wales border, and re-establishment of the station at Bromelton may be what is intended by the term 'New Beaudesert line'.

No surface property resumptions were required under this revised plan. Dutton Park station was proposed to be closed, as it would need to be demolished as part of the project and the government stated that its patronage level of ~150 passengers per peak hour didn't justify the $150m cost to rebuild the station. Following public objections, particularly to the proposed walkways from Park Road station, 800 metres away (proposed to provide replacement access to the Princess Alexandra Hospital, the major facility adjacent to Dutton Park station), the government reversed its decision.[4][5][6][7]

The George street station was proposed to be built 48 metres below 63 George Street building on the corner of George and Mary Streets. The George Street building, which houses many state government departments, was to be demolished.[8] The Woolloongabba station was to be 38 metres below surface level, with the Roma Street station to be 31 metres below surface level. The ruling grade in the tunnel was proposed at 3.25% (~1 in 31).

2014 revision

On 30 November 2014, the State government announced a further revision to the plan affecting the northern section. The tunnel was now proposed to be situated at the western end of Roma St station, and involve the demolition of the Brisbane Transit Centre's west tower, with a new building to incorporate the BaT Roma Street station and the Transit Centre's bus terminal. The bus tunnel component was planned to connect to the Northern Busway between the Roma Street and Normanby busway stations, with a train-only tunnel to continue under the Normanby Busway station, with a northern portal in the Normanby rail yard, shortening the tunnel length by 1.4 km, to 4 km in total.

The reference design for the tunnel between Dutton Park railway station and Boggo Road busway station showed a 'knock out panel for possible future rail extension'.[9]

Cancellation

Following a change of State Government, in March 2015 the BaT Project was cancelled.[10]

See also

References

  1. "Overview, BaT Tunnel, TMR". Department of Transport and Main Roads. 1 December 2014. Archived from the original on 4 January 2015. Retrieved 4 January 2015.
  2. Double-deck rail and bus tunnel proposed for Brisbane Railway Gazette
  3. "Underground Bus and Train". Queensland Government Department of Main Roads. 2013-11-22. Retrieved 5 December 2013.
  4. "Brisbane's BaT project planning takes flight - but awaits funding" Railway Digest June 2014 pages 28-31
  5. BaT changes include Dutton Park railway station and Victoria Park Queensland Government 25 June 2014
  6. Queensland Government not closing Dutton Park train station for BAT Tunnel ABC News 25 June 2014
  7. "Dutton Park station to remain" Railway Digest August 2014 page 14
  8. Tony Moore (19 March 2014). "Brisbane transit tunnel named". Retrieved 10 April 2014.
  9. BaT Tunnel Maps Queensland Government
  10. BaT Tunnel scrapped as government looks for different cross river rail line Brisbane Times 6 March 2015

External links

This article is issued from Wikipedia - version of the 10/23/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.