Brenner Base Tunnel

Brenner Base Tunnel
Overview
Location Brenner Pass
Status Under Construction
System Brenner railway
Start Innsbruck, Austria
End Franzensfeste, Italy
Operation
Work begun 2008
Constructed 2006–
Opened Scheduled 2026
Traffic freight trains and passenger trains
Character Twin tube
Passenger and Freight
Technical
Length 55 km (34 mi)
No. of tracks Double track
Track gauge 1,435 mm (4 ft 8 12 in) standard gauge
Electrified Electrified
25kV 50 Hz AC
Operating speed 250 km/h (160 mph) Passenger
160 km/h (99 mph) Freight
Highest elevation 840 metres (2,760 ft)
Grade Austria 7.4/1000
Italy 5/1000

The Brenner Base Tunnel (German: Brennerbasistunnel; Italian: Galleria di base del Brennero) is a planned 55-kilometre (34 mi) long railway tunnel through the base of the Eastern Alps beneath the Brenner Pass. It will run from Innsbruck Hauptbahnhof in Austria to Franzensfeste (Fortezza) in Italy, replacing part of the current Brenner railway.[1] The line is part of Line 1, the Berlin to Palermo route, of Trans-European Transport Networks (TEN-T).

The Brenner Pass, in the Alps at the border between Austria and Italy, is one of the most important traffic connections between northern and southern Europe, and the motorway going over it is infamous for its frequent traffic jams. Pollution from this traffic is a major concern.

The hope is to relieve this situation by greatly improving the railway connection between North Tyrol and South Tyrol with the new tunnel, which will allow trains to cross the Alps much faster. Currently, speeds in the Brenner region barely exceed 70 km/h (43 mph) due to the steepness of the existing tracks, which cross the pass at a rather high elevation.

The project is funded by Austria and Italy, and a contribution by the European Union. Due to the magnitude of the project (it will be the world's second longest tunnel, after the Gotthard Base Tunnel), the funding promised so far will not suffice for the estimated costs. The tunnel is scheduled to be completed in 2025.[2]

The travel time from Innsbruck to Bolzano will be reduced from 2 hours to 50 minutes.[3]

Background

Brenner Base Tunnel
Legend
Lower Inn railwayfrom Rosenheim
Lower Inn railwayto Innsbruck
bridge on Inn
Innsbruck bypassNorth portal
Ampass shaft
Brenner Base shaftNorth portal to Innsbruck
Ahrental shaft
Wolf shaft
Italy-Austria border
Mauls/Mules shaft
Aicha/Aica shaft
Brenner Base TunnelSouth portal
Brenner railwayto Brenner/Brennero
Franzensfeste/Fortezza
Brenner railwayto Brixen
Riggertal/Val Riga shaft
Albeins/Albes shaft
Eisack/Isarco bridge
Brenner Railway
Klausen/Chiusa shaft
Brenner railwayto Waidbruck/Ponte Gardena
Brenner railwayto Bolzano/Bozen
Laives/Leifers-Steinmannwald shaft
Brenner railwayto Bolzano/Bozen
Brenner railwayfrom Verona

The passenger and freight traffic across the Alps has increased greatly in recent years and further growth is forecast. Austria is a key country in movement of freight between northern and southern Europe and between eastern and western Europe. The Brenner region is very politically sensitive with respect to both local and cross-border transport issues. Between 1970 and 1999, highway freight increased seven-fold. (3 million to 22 million tonnes) In 1990, 70% of the freight from eastern Europe was transported by rail and the remainder by trucks. These proportions were expected to reverse by 2010.[4]:182ff About three-quarters of traffic through the Brenner Pass is currently carried by road transport. Local residents have long fought for relief from the associated pollution. The construction of a rail tunnel is considered by its proponents to be necessary for a shift of freight traffic from road to rail.

The railway line from Innsbruck to Bozen was built between 1860 and 1867. Tight curve radii and gradients of up to 2.5% complicate rail operations. However, improvements on the Italian side in recent years to the existing line, which were completed in late 2008, allow the line theoretically to accommodate 240 trains per day. The grades were not significantly improved.

The new Brenner line would have a maximum gradient of 1.2% and the gradient in the tunnel would be about 0.7%. Thus, a locomotive would be capable of hauling more than double the weight. The new line (the base tunnel together with the southern approach from Waidbruck/Ponte Gardena to Franzensfeste/Fortezza) would cut travel time between Innsbruck and Bozen from about two hours today to less than half that.

Project

Main tunnel

Start of the Tunnel boring machine at Aicha/Aica construction site in April 2008
View of Mauls/Mules construction site in summer of 2008

The 55 kilometres (34 mi) long, twin-tube tunnel begins in the Innsbruck suburb of Wilten and penetrates the Alps reaching a height of about 840 metres (2,760 ft) above sea level (ASL). The tunnel will be up to 1,600 m (5,200 ft) below the surface at its deepest point in the gneiss section stretching south from the Italian border.[5] Since under the most recent plan the tunnel starts as a twin-tube tunnel, the junction already prepared in the Inntal tunnel on the Innsbruck bypass will not be used. Instead, a costly diversion with several branches is planned.

The volume of rock to be excavated during the construction of the tunnel is estimated at 11.1 million cubic metres (390 million cubic feet), of which approximately 6.8 million cubic metres (240 million cubic feet) will be incurred in Austria, as about 60% of the tunnel will be in Austria. About 6 million cubic metres (210 million cubic feet) of the spoil will be used as fill for the approach lines. 2.35 million cubic metres (83 million cubic feet) in the concrete aggregate and 2.75 million cubic metres (97 million cubic feet) will be used for line side embankments and revegetation. The main tunnels will have a circular cross section with a diameter of 9.6 m (31 ft).

According to current planning the apex of the tunnel will be at the border at an altitude of about 810 m (2,660 ft) ASL, although an apex farther south would have been lower. The placing of the apex at the border is set out in the treaty between Austria and Italy. As justification for this choice it is stated that this will allow Austrian water to run in the tunnel to Austria and Italian water to Italy. The Austrian section of the tunnel will have a gradient of 0.74% and the Italian section will have a gradient of 0.5%.

Northern approach

BBT construction site in Sill river seen from Bergisel in April 2011

On its north end, the base tunnel (BBT) has two entrances, which must go underground a few kilometres before the junction with the main tunnels, and will also be built as part of the BBT. One route leads from the main Innsbruck station under Bergisel and the other connects with the Innsbruck bypass. This route adds about 8 kilometres (5.0 mi) more to the length of the tunnel than the Innsbruck station route; with it included, the BBT, at 62.7 kilometres (39.0 mi), would become the longest continuous railroad tunnel in the world. However, if the Axentunnel extension is added to the Gotthard base tunnel, its length would become 75 kilometres (47 mi), allowing it to reclaim the 'longest tunnel' title.

The northern approach from Munich within Germany is the 165 kilometres (103 mi) GrafingRosenheim–Kufstein route. A more direct route between Munich and Innsbruck, for example, via Garmisch-Partenkirchen, Mittenwald and Seefeld was not pursued, though it could have shortened the Munich Innsbruck line to 129 kilometres (80 mi).

Concrete shell for the New Lower Inn Valley railway during completion in 2007

In Austria, a new double-track high-speed line supplements the Lower Inn Valley railway between Wörgl and Baumkirchen. About 32 kilometres (20 mi) of the 40 kilometres (25 mi) line through the Lower Inn Valley (Unterinntal) is built underground, in troughs, or under snow sheds. Noise and vibration mitigation is accomplished by the use of 80,000 square metres (860,000 sq ft) of elastomer in a mass-spring system. The segment's track superstructure is load class E5. It is capable of handling 260-300 trains per day.[1] This section was opened 2012-12-09.[6] Planning is under way on the continuation of this line to the German border at Brannenburg. There is currently no firm commitment to upgrade the two-line railway from Grafing to Brannenburg.

Southern approach

The southern approach for the BBT will be 189 kilometres (117 mi) long and reach from the southern portal of the tunnel in Franzensfeste/Fortezza to Verona. Planning has been completed for some sections.

The Italian government has budgeted €6 billion for the construction of the entire southern approach. Critics consider this estimate too optimistic and fear that the project will fail because of high construction costs.

History

The Brenner tunnel is the most important link in the Berlin–Palermo railway axis, a series of projects that will create a single railway line from Berlin in Germany to Palermo in Sicily.

Schedule history

Early in the preliminary planning, at a Brussels meeting in June 2005, BBT SE (Brenner Base Tunnel Societas Europae), presented an interim status report. Expectations following the meeting were that the project could be finalized and the pilot tunnel started by 2006. The target for the tunnel to start service was 2015.[7][8]

In 2007 a construction time line with a 2022 finish date was specified in a memorandum signed by the Austrian and Italian ministers of transport.[9]

By May 2009 the completion date was changed to be by 31 December 2025.[10]

Funding history

On December 2008 Antonio Tajani, the European commissioner for transport, approved funds totalling €1.7 billion to finance 11 railway projects that together should establish two major routes across the continent.[11][12]

In May 2009 it was confirmed that final go-ahead for the project had been given.[10]

The final estimated cost was put at €6bn at 2006 levels.[9]

Construction history

In the summer of 2006 work started on a pilot tunnel to run along the line of the future tunnel and to be used for removing water and spoil during the major construction phase. Construction of the pilot tunnel between 2006 and 2009 was estimated to cost €430 million and would be 50% EU funded.

Design

The final design will consist of two tunnels, 55 kilometres (34 mi) long. A centre tunnel 12 metres (39 ft) below the two primary tunnels will be used during construction as a guide tunnel to determine geological conditions, and later for drainage and emergency access. There will be a cross over between the tunnels every 333 metres (1,093 ft). Multi-function stations will be located at Trens (in Freienfeld), Steinach, and a third station towards the northern end of the tunnel to provide operational and emergency services. ETCS Level 2 will be installed to provide train control.[10]

Specifications[13]

See also

References

  1. 1 2 "Case Study: Northern Approach Line to the Brenner Base Tunnel" (PDF). getzner. September 2010. p. 4. Retrieved 2014-01-08.
  2. "IEWY news: Green light for Brenner Base Tunnel". 2011-04-19.
  3. Müller-Meiningen, Julius (2008-04-30). "Monumentales Superloch". Sueddeutsche Zeitung (in German).
  4. ff Contemporary Issues and Debates in EU Policy: The European Union and ..., p. PA182 ff, at Google Books ISBN 071906418X
  5. "www.tunneltalk.com". Retrieved 2013-08-14.
  6. "Neue Unterinntalbahn: Highspeed und höchste Sicherheit" (PDF) (in German). ÖBB-holding AG. 2012-11-26. p. 3. Archived from the original (PDF) on 2013-09-30. Retrieved 2014-01-08.
  7. "EC welcomes progress - Brenner Base tunnel project". Retrieved 2013-08-16.
  8. "EUROPA - Press Release - Commission welcomes progress of Brenner Base tunnel project". Retrieved 2013-08-16.
  9. 1 2 van Miert, Karel (2007-09-10). "Annual activity report by the coordinator Karel Van Miert - PRIORITY PROJECT 1 Berlin-Verona/Milan-Bologna-Naples-Messina-Palermo rail link" (PDF). Retrieved 2007-12-09.
  10. 1 2 3 "Railway Gazette: Brenner base tunnel approved". 11 May 2009. Retrieved 2010-10-18.
  11. "Brenner Tunnel: construction of the exploratory gallery begins" (Press release). European Commission. 2006-06-29. Retrieved 2006-12-13.
  12. "Railway Gazette: TEN-T rail funding signed". Retrieved 2010-10-18.
  13. "Basic data – BBT SE". Galleria di Base del Brennero - Brenner Basistunnel BBT SE. Retrieved 19 February 2013.
  14. "Brenner project takes a major leap forward". TunnelTalk.com. February 2011. Retrieved 19 February 2013.
Wikimedia Commons has media related to Brenner Basistunnel.

Coordinates: 47°3′24″N 11°29′59″E / 47.05667°N 11.49972°E / 47.05667; 11.49972

This article is issued from Wikipedia - version of the 11/19/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.