ETRR-2

(Multi-Purpose) Experimental Training Research Reactor No. 2

Location of (Multi-Purpose) Experimental Training Research Reactor No. 2

Operating Institution Nuclear Research Center
Location Inshas, Egypt
Coordinates 30°17′35.0″N 31°24′32.5″E / 30.293056°N 31.409028°E / 30.293056; 31.409028Coordinates: 30°17′35.0″N 31°24′32.5″E / 30.293056°N 31.409028°E / 30.293056; 31.409028
Type Light Water Pool-type reactor
Power 22 MW (thermal)
Construction and Upkeep
Construction Cost US$75 million
Construction Began December 1, 1992 (1992-12-01)
First Criticality November 27, 1997 (1997-11-27)
Annual Upkeep Cost US$6 million
Staff 25
Operators 8
Technical Specifications
Max Thermal Flux 2.8E14
Max Fast Flux 2.2E14
Cooling Light Water
Neutron Moderator Light Water
Neutron Reflector BE
Control Rods AG,IN,CD
Cladding Material Aluminum Alloy

Source(s): [1][2][3][4]

Website
www.eaea.org.eg

ETRR-2 or ET-RR-2 (Experimental Training Research Reactor Number two), (Egypt Test and Research Reactor Number two)[5] or (Multi-Purpose Reactor) is the second nuclear reactor in Egypt supplied by the Argentine company Investigacion Aplicada (INVAP) in 1992.[6] The reactor is owned and operated by Egyptian Atomic Energy Authority (AEA) at the Nuclear Research Center in Inshas, 60 kilometers northeast of Cairo.[7]

History

Since 1990, Egypt started to search for a new research reactor to replace the aging ETRR-1 and the Israeli press claimed that Egypt was cooperating with Pakistan, Iraq and Argentina to build a plutonium-producing reactor for nuclear weapons. Finally, Egypt announced international tender and among the bidders were the Canadian Atomic Energy of Canada Limited, the French Framatome and the Argentinian INVAP.[8]

On September 1992, a contract was signed between INVAP and the Egyptian Atomic Energy Authority (AEA) and a branch office of INVAP in Nasr City was established to oversee the project with the construction works began in 1993 jointly by Argentina and Egypt.[9]

On November 1997, ETRR-2 achieved initial criticality, and was inaugurated by the former Egyptian president Hosni Mubarak and the Argentine president Carlos Menem on February 1998.[9]

Overview

The ETRR-2 reactor hall, showing the main and auxiliary pools.

ETRR-2 is a Material Testing Reactor (MTR),[10][11] multi-purpose open pool type 22 MW reactor[12][13] with an initial fuel load of 19.75% enriched uranium U235 imported from Russia and the last shipment was delivered by Argentina in 1997. Since that, Egypt has fabricated the fuel rods for the ETRR-2 from the Fuel Manufacturing Pilot Plant (FMPP), which is located at the Nuclear Research Center in Inshas.[13][14] The reactor core is cooled and moderated by light water and beryllium reflector. The spent fuel from the ETRR-2 reactor stored in a water-filled spent fuel pool near the reactor waiting for final disposal in deep geological formations.[13][15]

According to the Wisconsin Project on Nuclear Arms Control and the International Institute for Strategic Studies, ETRR-2 could produce over 6 kg of plutonium annually which is enough for one nuclear weapon per year.[13][14][16]

Unreported nuclear experiments

In 2004/2005, an investigation by International Atomic Energy Agency (IAEA) discovered that between 1999 and 2003, Egypt conducted about 4 unreported experiments using a total of 0.24 g of natural uranium compounds irradiated at the ETRR-2 to test the production of fission product isotopes for medical purposes. The irradiated compounds had been dissolved in three laboratories located in the Nuclear Chemistry Building with no plutonium or U-233 was separated during these experiments. Also, during the investigation Egypt disclosed the Radioisotope Production Facility which was a new facility under construction at Inshas, designed for the separation of radioisotopes from enriched 19.7% U-235 irradiated at the ETRR-2 reactor. Egypt should have reported the decision to construct the new facility no later than 1997.[17][18][19]

Egypt justified its reporting failures as the government and the IAEA had “differing interpretations” of Egypt’s safeguards obligations and emphasizing that the country’s “nuclear activities are strictly for peaceful purposes”[17] accordingly, Egypt maintained fully cooperated during the 2004/2005 investigation and had taken corrective actions by submitting inventory change reports (ICRs) and providing a modified design information for the ETRR-2 reactor and the Radioisotope Production Facility.[14][18][19][20]

In 2009, The IAEA's Safeguards Implementation Report (SIR) for 2008, concludes that earlier issues of undeclared nuclear activities and material reported to the Board of Governors in February 2005 are no longer outstanding as the IAEA found no discrepancies between what have been declared during the investigation and IAEA's findings and no evidences of extraction of plutonium or enrichment of uranium.[14][18][21]

Reactor specifications

Data from [1][2][3]

General data

Technical data

Experimental facilities

Fuel data

Utilization

See also

References

  1. 1 2 Global Research Nuclear Reactors Handbook: Strategic Information and Nuclear Reactors in Selected Countries (Algeria, Germany). [S.l.]: Intl Business Pubns Usa. 2013. pp. 161–163. ISBN 1577514505. Retrieved 11 July 2014.
  2. 1 2 "Research Reactor Details - ETRR-2". iaea.org. International Atomic Energy Agency. Retrieved 17 July 2014.
  3. 1 2 "Research Reactors - ETRR-2". nucleus.iaea.org. International Atomic Energy Agency. Retrieved 30 August 2014.
  4. "Nuclear Research Center (NRC)". Nuclear Threat Initiative. James Martin Center for Nonproliferation Studies. Retrieved 9 April 2015.
  5. El-Messiry, A.M. "ETRR-2 control rod withdrawal accident". ScienceDirect. Elsevier Ltd. Retrieved 19 July 2014.
  6. Bissani, M.; O'Kelly, D. S. "Joint Assessment of ETRR-2 Research Reactor Operations Program, Capabilities, and Facilities" (PDF). Office of Scientific and Technical Information. University of California, Lawrence Livermore National Laboratory. Retrieved 19 July 2014.
  7. "ETRR-2 reactor (Egypt)". INVAP. Retrieved 9 April 2015.
  8. "Egypt's Budding Nuclear Program". Wisconsin Project on Nuclear Arms Control. Retrieved 3 September 2014.
  9. 1 2 Ragheb, M. "Safeguards, Non-Proliferation and Peaceful Nuclear Energy" (PDF). mragheb. Retrieved 9 April 2015.
  10. Gahieen, Mohamed A. (November 2008). "Utilization of Egyptian Research Reactor and modes of collaboration" (PDF). IAEA. Retrieved 7 May 2016.
  11. Shaat, M.K. (July 2010). "Products and Services of Research Reactors" (PDF). IAEA. Retrieved 7 May 2016.
  12. Villarino, Eduardo; Doval, Alicia (2011). "INVAP's Research Reactor Designs". Science and Technology of Nuclear Installations. 2011: 4. Retrieved 19 July 2014.
  13. 1 2 3 4 "ETRR-2". Nuclear Threat Initiative. James Martin Center for Nonproliferation Studies. Retrieved 19 July 2014.
  14. 1 2 3 4 Fitzpatrick, Mark (July 2011). "Nuclear capabilities in the Middle East" (PDF). nonproliferation.eu. EU Non-Proliferation Consortium. Retrieved 22 April 2015.
  15. Abdellatif, Magda; Sirag, Nadia (May 2015). "Proposal Sites for Spent Fuel Disposal in Egypt by Using GIS Program" (PDF). International Journal of Innovative Research in Science, Engineering and Technology. 4 (5): 2725. Retrieved 28 April 2016.
  16. Stock, Raymond (7 September 2012). "Egypt:The Muslim Brotherhood Bomb?". Gatestone Institute. Retrieved 22 April 2015.
  17. 1 2 Kerr, Paul (1 March 2005). "IAEA: Egypt's Reporting Failures 'Matter of Concern'". Arms Control Association. Retrieved 22 April 2015.
  18. 1 2 3 "Implementation of the NPT Safeguards Agreement in the Arab Republic of Egypt" (PDF). globalsecurity.org. International Atomic Energy Agency. Retrieved 21 April 2015.
  19. 1 2 "Radioisotope Production Facility". Nuclear Threat Initiative. James Martin Center for Nonproliferation Studies. Retrieved 22 April 2015.
  20. Nartker, Mike (14 February 2005). "Egypt Failed to Report "A Number" of Nuclear Materials, Activities, Facilities, IAEA Says". Nuclear Threat Initiative. Global Security Newswire. Retrieved 22 April 2015.
  21. "IAEA/EGYPT: Safeguards Implementation Report Cites Investigation of LEU/HEU Particles Found at Inshas Nuclear Center". Vienna: WikiLeaks. 8 May 2009. Retrieved 8 May 2015.
This article is issued from Wikipedia - version of the 7/27/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.