Elwha Dam
Elwha Dam | |
---|---|
Elwha Dam in 2005 | |
Location | Clallam County, Washington, USA |
Construction began | 1910 |
Opening date | 1913 |
Demolition date | 2012 |
Dam and spillways | |
Impounds | Elwha River |
Height | 105 ft (33 m) |
Reservoir | |
Creates | Lake Aldwell |
Power station | |
Installed capacity | 14.8 MW[1] |
Elwha River Hydroelectric Power Plant | |
| |
Nearest city | Port Angeles, Washington |
Area | 3.5 acres (1.4 ha) |
Built | 1911 |
Architect | Summers,L.L., & Co. |
Architectural style | Other, Concrete gravity dam |
MPS | Hydroelectric Power Plants in Washington State, 1890--1938 MPS |
NRHP Reference # | 88002741[2] |
Added to NRHP | December 15, 1988 |
The Elwha Dam was a 108-ft (33 m) high dam located in the United States, in the state of Washington, on the Elwha River approximately 4.9 miles (7.9 km) upstream from the mouth of the river on the Strait of Juan de Fuca.
The Elwha River Ecosystem and Fisheries Restoration Act of 1992 authorized the US Federal Government to acquire the Elwha Dam and Glines Canyon Dam hydroelectric power projects for decommissioning and demolition for habitat restoration. Removal of the Elwha Dam began in September 2011 and was fully complete by March 2012, allowing the Elwha River to flow freely through the site.
Construction
The dam was built under the direction of Thomas Aldwell. Aldwell previously bought up tracts of land around the river, and with the help of Canadian financier George Glines, began construction of the Elwha Dam in 1910. Aldwell and his contractors cut corners on constructing the dam, including not building fish passages and did not secure it to the bedrock.[3] Thus, in 1912, as the reservoir filled behind the nearly completed dam, the lower sections of the dam gave way and a torrent of water headed downstream, taking out a bridge. Aldwell was able to get funding for reconstructing the dam and it was completed in 1913. The reservoir that filled the valley behind was known as Lake Aldwell. The dam was listed on the National Register of Historic Places in 1988.[4]
Initially, along with the Glines Canyon Dam, which was completed in 1926, it helped to fuel economic growth and development for the Olympic Peninsula and the community of Port Angeles, Washington. However, by the early 21st Century, the combined power output of both dams only provided the equivalent of 38% of the electricity needed to operate one paper mill, the Daishowa America mill.
Lacking passage for migrating salmon, its construction blocked access by anadromous salmonids to the upper 38 miles (48 km) of mainstem habitat and more than 30 miles (48 km) of tributary habitat. The salmon runs that once numbered more than 400,000 adult returns in over 70 miles (110 km) of available habitat, now numbered less than 4,000 adult returns on only 4.9 miles (7.9 km) of available habitat.
Effects of dam on river habitat
After the construction of the dams, the lower reach of the river saw a drastic decrease in sediment delivery. This led to a net erosion of the riverbed, including the gravels needed to create suitable habitats for spawning. Replacement gravel was trapped in the sediment load behind the dams.[5] These gravels are considered an essential resource for restoration of salmon habitats.[6] The delta at the mouth of the river, where it enters the Strait of Juan de Fuca, also saw a net erosion effect, confirmed by local tribal leaders.[5]
Another effect of damming was the creation of Lake Aldwell and Lake Mills. These lakes had a multitude of impacts on the river beyond sediment retention. Because the water stayed in the lake for so long, it warmed up to approximately 16 °C.[7] Normal water temperatures are around 0 °C.[8] These higher temperatures are unnatural for spawning fish, which prefer colder ocean temperature waters. This increase in temperature also increases parasite populations.[5] Disease was known to wipe out two thirds of a spawning population, before it had a chance to spawn.[5] The lakes also acted as buffers for high and low flow conditions. While the dams were not actively used for flood control, the reservoirs behind them altered the natural flow patterns of the river. The normal seasonal high and low flow were evened out by the reservoirs and dams so that flow was relatively constant throughout the year. Natural flow patterns are known to promote the health of native species and to help eliminate non native species after dam removal.[9]
History of the Elwha fishery
At its peak, the Elwha supported spawning runs of Chinook, Coho, Chum, Pink, and Sockeye Salmon as well as Steelhead, Cutthroat, and Bull Trout. The Chinook were known to reach sizes of 45 kg. Sockeye, Chinook, Chum, and Pink Salmon were all endangered in the Elwha. Leaving one or both of the dams in place, even with modern fish passage systems, would not result in a dramatic recovery of species due to other factors like water temperature, gravel beds, etc. which would still have negative effects on the fish species (see Table 1). The most valuable spawning habitats are located far upstream from the Glines Canyon Dam, so it still acted as a major barrier to the recovery of the runs. Removal of both dams was thus considered the only viable option for full restoration of the river and habitat.
Dam removal
The Elwha River Ecosystem and Fisheries Restoration Act of 1992 created funding and government support for mitigation of the dams on the Elwha. While fish ladders were proposed as a possibility, they were ultimately ruled out for the reasons above. The major problem raised with regard to removal of the two dams was the approximately 34 million cubic yards of sediment that had built up behind the dams.[11] Of that 34 million, 28 million was behind the Glines Canyon Dam, while 6 million was behind the Elwha Dam. Releasing all of this sediment at once would have devastating effects on the remaining habitats downstream from the dams, as well as along beaches at the coast. A drawdown experiment was conducted on the Glines Canyon Dam to assess the erosion of the sediments from Lake Mills.[12] The lake was drawn down 18 feet (5.5 m) over one week and then allowed to remain stable for one more week. This test showed that the river would rapidly cut into the existing delta as soon as the lake level dropped, creating a deep, narrow channel. A new delta immediately began to form at the new lake level. Once the lake level was held steady, the channel migrated laterally along the existing delta. This test resulted in a sediment erosion model in which gradual drawdown of the lake would result in a greatly decreased sediment load downstream. Using this model, the plan was to drain the lake gradually over a two-year time period, allowing much of the sediment to remain in the old lake basin.
The model showed that after the two year dam removal period, the river would begin to restore itself to natural conditions. Sediment discharge rates would increase, resulting in restored and rejuvenated habitats downstream from the dams. Fish were anticipated to return to the upper reaches of the Elwha as soon as a year after dam removal was complete.[13] While the river might never return to historically large runs, after 15–20 years or more, there should be a recovery of salmon runs to some sort of "pre-dam" condition.[5] In addition to restoring the fish habitats, the draining of Lake Mills and Lake Aldwell would create an additional 715 acres (2.9 km2) of terrestrial vegetation, improving elk habitats[9] (Figure 1). Increased sediments loads were also predicted to help restore the retreating delta at the mouth of the Elwha.
Removal of the dams on the Elwha River has been a long process. Physical removal started on September 27, 2011 and was completed August 26, 2014.[14][15] There is uncertainty about how the river will transform itself and what period of time will be involved. Because so few dam removal projects have been accompanied by scientific study, perhaps fewer than 20,[13] this project will be a model of the effectiveness of dam removal on this scale. If restoration of the river is successful, it could encourage a movement towards the restoration of natural stream morphology through the removal of larger dams. Most fish populations are expected to make a return to the river (Table 1). While fish may return to the river as soon as a year after the removal is complete,[13] it may take 15 to 20 years for the river to fully return to its pre-dam conditions.[5] The ultimate goal of the dam removal is restoring the river to a nearly pristine state.[15]
- September 17, 2011
- February 14, 2012
- May 23, 2013
See also
Footnotes
- ↑ "Restoring Rivers: Major upcoming dam removals in the Pacific Northwest" (PDF). www.water.ca.gov. Retrieved 21 June 2016.
- ↑ National Park Service (2010-07-09). "National Register Information System". National Register of Historic Places. National Park Service.
- ↑ Lichatowich, Jim; Lichatowich, James A. (2001). Salmon Without Rivers: A History of the Pacific Salmon Crisis. Island Press. pp. 132–135. ISBN 978-1-55963-361-1. Retrieved 23 October 2011.
- ↑ "National Register of Historical Places record for Elwha River Hydroelectric Power Plant" (PDF). Retrieved 2012-06-17.
- 1 2 3 4 5 6 7 Wunderlich, 1994
- ↑ Bureau of Reclamation, 1996
- ↑ USGS, 2005
- ↑ USGS 2005
- 1 2 American Rivers, 2002
- ↑ Hart et al. 2002
- ↑ Randle, 2012
- ↑ Randle, 2001
- 1 2 3 Hart et al., 2002
- ↑ nps.gov
- 1 2 ALEXANDRA WITZE (December 30, 2014). "Dam demolition lets the Elwha River run free;". Science News. Retrieved 2015-01-04. (Subscription required.)
References
- Wunderlich, R. C., B. D. Winter, and J. H. Meyer. 1994. Restoration of the Elwha River ecosystem. Fisheries 19, no. 8:11-20.
- U.S. Department of Interior, Bureau of Reclamation. 1996. Sediment Analysis And Modeling Of The River Erosion Alternative. Elwha Technical Series, PN-95-9.
- USGS. 2005. Hoko, Elwha, and Dungeness River Basins. http://pubs.usgs.gov/wdr/2005/wdr-wa-05-1/pdf/wa00103ADR2005_Figure14.pdf
- American Rivers (Organization). 2002. The ecology of dam removal: a summary of benefits and impacts. Washington, DC: American Rivers.
- Proceedings of the Seventh Federal interagency sedimentation conference. United States (USA):2001.
- Hart, D. D., et al. 2002. Dam Removal: Challenges and Opportunities for Ecological Research and River Restoration. Bioscience 52, no. 8:669-682.
- National Park Service. Elwha River Projected Timeline. http://www.nps.gov/archive/olym/elwha/history.htm
External links
Wikimedia Commons has media related to Elwha Dam. |
- Elwha River Ecosystem and Fisheries Restoration Act of 1992
- Elwha River Restoration – National Park Service
- Webcam and time lapse animation of dam removal project
- Elwha Dam Removal Animation
- Historic American Engineering Record (HAER) No. WA-130-A, "Elwha River Hydroelectric System, Elwha Hydroelectric Dam & Plant, Port Angeles vicinity, Clallam County, WA"
- Undamming the Elwha Documentary produced by KCTS-TV
- Mapes, Lynda V. (February 13, 2016), "Elwha: Roaring back to life", The Seattle Times
Coordinates: 48°5′42″N 123°33′23″W / 48.09500°N 123.55639°W