Job costing

Job costing Job costing requires direct labour, direct materials, warranty, quality control and other hidden overhead costs. Then the estimated manufacturing costs are deducted from the Cost of Sales, resulting in an apparent profit.

It involves the calculation of costs involved in a construction "job" or the manufacturing of goods done in discrete batches. These costs are recorded in ledger accounts throughout the life of the job or batch and are then summarized in the final trial balance before the preparing of the job cost or batch manufacturing statement.

Job costing vs. process costing

Job costing (known by some as job order costing) is fundamental to managerial accounting. It differs from Process costing in that the flow of costs is tracked by job or batch instead of by process.

The distinction between job costing and process costing hinges on the nature of the product and, therefore, on the type of production process:

Using job costing

Job Costing is the process of determining the labor and materials cost for each job in a systematic way, and then using this information to create a quote for the customer. Job costing or cost accounting can be used in virtually any industry (especially service industry) to ensure that the product pricing covers actual costs, overhead and provides a profit. The purpose of any business is to make money, and job costing is the most effective way to ensure that occurs.In a job costing system, costs may be accumulated either by job or by batch. For a typical job, direct material, labor, subcontract costs, equipment, and other direct costs are tracked at their actual values. These are accrued until the job or batch is completed. Overhead or "burden" may be applied either by using a rate based on direct labor hours or by using some other Activity Based Costing (ABC) cost driver. In either case, once overhead/burden is added, the total cost for the job can be determined. If the accountant is using a general ledger accounting system, which lacks true job costing functionality, the costs must be manually transferred out of Work in Process to Finished Goods (Cost of Goods Sold for service industries). Of course, in the days of computerized job costing software, journaling costs manually is an obsolete process. Such hand-journaling is mandatory for companies that continue to use general accounting software to do job costing. Enlightened accountants are moving forward and using job costing software, thereby improving cost control, reducing risk, and increasing the chance of profitability.

Using cost codes in budgeting

In a true job cost accounting system, a Budget is set up in advance of the job. As actual costs are accrued, they are compared to budgeted costs, to determine variances for each phase of each job. Cost Codes are used for each phase, allowing "mini-budgets" to be generated and tracked. In the construction industry, the Construction Specifications Institute (CSI) has established an industry standard Cost Coding system.job costing system consists of various cost driver that drives job cost, moreover it

Example

These examples will assume that overhead is allocated on the basis of Direct Labor Hours. Direct Material is abbreviated DM, Direct Labor as DL, and Overhead as OH.

XYZ corporation manufactures airplanes. 1 order was completed (#110), 2 received further work (#111, 112), and 1 new order was received (#113). Overhead is allocated at a rate of $100/DL Hour. All employees earn $20/hour. Beginning Work In Process Balances are as follows: #110, $25,000; #111, $10,000; #112, $12,000; #113 $0 (New Order). Below are the amounts of DM and DL used.

Caution: Remember, overhead is allocated on the basis of DL hours. While in this case, allocating overhead on the basis of DL cost ($5 of overhead for every $1 DL cost) would produce the same result, this may not always be the case. Since rates are developed based on a budget, if employees are actually paid a different rate from the budgeted rate, allocating at a $5 to $1 ratio would produce a different cost from the stated $100/DL hour allocation. Companies use slightly different overhead allocation methods.

References

  1. Don R. Hansen and Maryanne M. Mowen (2006). Cost Management Accounting & Control. Ohio: Thomas South-Western. pp. ????. ISBN 0-324-00232-7.