Upper Cisokan Pumped Storage Power Plant
Upper Cisokan Pumped Storage Power Plant | |
---|---|
Location of Upper Cisokan Pumped Storage Power Plant in Indonesia | |
Official name | Upper Cisokan Pumped Storage Hydro Electric Power Plant |
Country | Indonesia |
Location | West Java |
Coordinates | 6°56′52″S 107°13′07″E / 6.94778°S 107.21861°ECoordinates: 6°56′52″S 107°13′07″E / 6.94778°S 107.21861°E |
Status | Preliminary construction |
Construction began | 2014 |
Commission date | 2019 est. |
Construction cost | US$800 million |
Owner(s) | Perusahaan Listrik Negara |
Pumped-storage power station | |
Upper reservoir | Cirumamis Reservoir |
Upper res. capacity | 14,000,000 m3 (11,350 acre·ft) |
Penstocks | 2-4 |
Lower reservoir | Cisokan Reservoir |
Lower res. capacity | 63,000,000 m3 (51,075 acre·ft) |
Hydraulic head | 276 m (906 ft) |
Pump-generators | 4 x 260 MW (275 MW in pump-mode) Francis pump-turbines |
Power generation | |
Nameplate capacity | 1,040 MW |
The Upper Cisokan Pumped Storage Plant will be located 40 km (25 mi) west of Bandung in West Java, Indonesia and will occupy area in West Bandung Regency and Cianjur Regency.[1] After receiving funding from the World Bank, construction on major works is expected to begin in 2015 and the first generator commissioned in 2019. It will have an installed capacity of 1,040 MW and will be Indonesia's first pumped-storage power plant. As a pumped-storage power plant, the project includes the creation of an upper and lower reservoir; the lower reservoir will be on the Upper Cisokan River a branch of Citarum River,[2][3] while upper reservoir will be on the Cirumanis River, a branch of the Cisokan River.
Background
Studies for the project were carried out in the 1990s and a detailed design was completed in 2002. A World Bank loan for the project was approved in May 2011 and signed in November. The West Java government approved the project in October 2011. Preliminary construction such as access road building began in early 2014.[4][5] The first generator should operational by 2019.[6][7][8] Of the project's US$800 million cost, US$640 million is being provided by the World Bank. The remaining US$160 million is to be supplied by the project owner Perusahaan Listrik Negara.[9]
Design and operation
The power plant will operate by shifting water between two reservoirs; the lower reservoir on the Upper Cisokan River and the upper reservoir on the Cirumamis River which is a right-bank tributary of the Upper Cisokan. When energy demand is high, water from the upper reservoir is sent to the power plant to produce electricity. When energy demand is low, water is pumped from the lower reservoir to the upper by the same pump-generators. This process repeats as needed and allows the plant to serve as a peaking power plant.[2]
Both reservoirs will be formed by concrete gravity dams using roller-compacted concrete. Each will have an overflow spillway at the center of their center. The upper reservoir's dam will be 75.5 m (248 ft) tall and 375 m (1,230 ft) long while the lower reservoir dam will be 98 m (322 ft) high and 294 m (965 ft) in length. The lower reservoir dam will trap water from a 355 km2 (137 sq mi) catchment area to create a lake with a gross storage capacity of 63,000,000 m3 (51,075 acre·ft). Of the total capacity, 10,000,000 m3 (8,107 acre·ft) can be used for pumping up to the upper reservoir. The surface area of the lower reservoir will be 260 ha (1 sq mi). The upper reservoir dam will trap water from a much smaller catchment area, 10.5 km2 (4 sq mi), to create its reservoir with a gross storage capacity of 14,000,000 m3 (11,350 acre·ft) and surface area of 80 ha (0 sq mi). Of that capacity, 10,000,000 m3 (8,107 acre·ft) is active (or usable) storage for power generation.[2]
The power plant will be located underground near the lower reservoir. Connecting the upper reservoir and the power plant will first be two headrace tunnels, one 1,220 m (4,003 ft) long and the other 1,160 m (3,806 ft) in length. Surge tanks on each headrace tunnel help prevent water hammer. Each headrace tunnel connects to a steel-lined penstock, each of which later bifurcates into two penstocks. Each of these four penstocks will supply water to the turbines during power generation. After power generation the water will be discharged into the lower reservoir via four tailrace tunnels. When pumping water moves through the same conduits back to the upper reservoir. The power plant will contain four Francis pump-turbines which are rated at 260 MW each for power generation and 275 MW for pumping. The upper reservoir will lie at maximum elevation of 796 m (2,612 ft) and the lower at 499 m (1,637 ft). This difference in elevation will afford the power plant a rated hydraulic head of 276 m (906 ft).[2]
See also
References
- ↑ "Pembangunan PLTA Cisokan Selesai 4 Tahun". Retrieved September 1, 2012.
- 1 2 3 4 "Indonesia - Upper Cisokan Pumped Storage Power Project". Project Appraisal Document. World Bank. April 2011. Retrieved 3 February 2012.
- ↑ "Upper Cisokan Pumped Storage Power Project". Aid Data. Retrieved 3 February 2012.
- ↑ "Implementation Status & Results Indonesia Upper Cisokan Pumped Storage Hydro-Electrical Power (1040 MW) Project (P112158)" (PDF). World Bank. 11 February 2013. Retrieved 13 February 2013.
- ↑ "Concerned Citizens landslide Cisokan Access Road Project" (in Indonesian). Pikiran Rakyat Online. 17 November 2014. Retrieved 21 December 2014.
- ↑ "PLTA Upper Cisokan Pumped Storage will immediately be built". Ministry of Energy and Mineral Resources (ESDM) Indonesia. 15 December 2011. Retrieved 3 February 2012.
- ↑ "Hydroelectric projects tendered Cisokan Start" (in Indonesian). Galamedia. 31 January 2012. Retrieved 4 February 2012.
- ↑ "Ready Cisokan Hydroelectric Power Boost Java-Bali" (in Indonesian). Fokus Jabar. 21 December 2014. Retrieved 21 December 2014.
- ↑ "Upper Cisokan Pumped Storage Hydro-Electrical Power (1040 MW) Project". World Bank. Retrieved 3 February 2012.