Wattle Point Wind Farm

Wattle Point Wind Farm

The information centre near the base of one of the towers.
Location of Wattle Point Wind Farm in South Australia
Country Australia
Location Edithburgh, South Australia
Coordinates 35°7′21″S 137°42′55″E / 35.12250°S 137.71528°E / -35.12250; 137.71528Coordinates: 35°7′21″S 137°42′55″E / 35.12250°S 137.71528°E / -35.12250; 137.71528
Status Operational
Commission date April 2005
Construction cost $180 million (AUD)
Wind farm
Type Onshore
Power generation
Units operational 55
Nameplate capacity 91 MW

Wattle Point Wind Farm is a wind farm near Edithburgh on the Yorke Peninsula in South Australia, which has been operating since April 2005. When it was officially opened in June of that year it was Australia's largest wind farm at 91 megawatts (122,000 hp). The installation consists of 55 wind turbines covering 17.5 square kilometres (6.8 sq mi)and was built at a cost of 180 million Australian dollars.[1] It is connected to ETSA Utilities electricity transmission system via a 132 kilovolt line.[2]

The location was chosen after identification as having one of mainland Australia's highest average wind speeds. The wind farm was officially opened by South Australian Premier Mike Rann and Southern Hydro Chairman, Dr Keith Turner.[3] The opening was opposed by some of the local Indigenous Australians, the Adjahdura (or Narungga). A descendant of the traditional landowners argued that construction desecrated an ancient burial ground, disturbing skeletons in the construction of turbine number four.[4] Work was halted in late 2004 after the discovery of human remains, artefacts and tools. The Aboriginal Affairs Department, and the developers, separately commissioned archaeological reports resulting in the development allowed to proceed with five towers being repositioned. Both reports concluded that the bones had come from elsewhere on the peninsula, being later reburied at Wattle Point. The region's aboriginal community was divided on construction; Narungga National Aboriginal Corporation supporting development and the Narungga Heritage Committee strongly opposing.[5]

Wattle Point Wind Farm was built and owned by Southern Hydro Pty Limited. Southern Hydro was owned by Meridian Energy of New Zealand until October 2005, when it was bought by the Australian Gas Light Company (AGL).[6] The windfarm was acquired by Alinta in October 2006, as part of an asset merger with AGL, and subsequently by the Australia and New Zealand Banking Group's Energy Infrastructure Trust, for 225 million dollars on 23 April 2007.[7]

The windfarm from the edge of Edithburgh.

The District Council of Yorke Peninsula approved a second wind farm, Wattle Point Stage 2. However it did not proceed due to insufficient capacity in the electrical transmission lines.[8]

See also

References

  1. "Wattle Point Wind Farm". District council of Yorke Peninsula. Archived from the original on 2007-08-30. Retrieved 2007-11-13.
  2. "Work underway on connection to Australia's largest wind farm". ETSA Utilities. 2004-09-07. Retrieved 2007-11-13.
  3. "Australia's Largest Wind Farm Opened In SA". The national newsletter of the Petroleum Exploration Society of Australia (77). August–September 2005. Retrieved 2007-11-13.
  4. "Traditional owners condemn wind farm opening". ABC News (Australia). 2005-06-21. Retrieved 2007-11-13.
  5. Bockmann, Michelle Wiese (2005-01-27). "Wind farm built on black heritage site". The Australian. p. 2.
  6. "AGL to build Australia's largest wind farm". Renewable Energy & Greenhouse Update February 2006. Freehills. 14 March 2006. Retrieved 2006-04-26.
  7. "(pdf)Purchase of Wattle Point Wind Farm Pty Ltd" (PDF). Australia and New Zealand Banking Group. 2007-04-23. Retrieved 2007-11-13.
  8. personal communication with Acting Director Development and Community Services, Yorke Peninsula Council

Media related to Wattle Point Wind Farm at Wikimedia Commons

This article is issued from Wikipedia - version of the 9/6/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.